The only projects that don't have risk are when it doesn't matter how long it will take, it doesn't matter how much it will cost, & it doesn't matter what will be implemented.
Brought to you by Project Assistant Try it.

Project management process, methods, and tools mitigate project risk.
All projects have some risk.
The key question is; how much risk is tolerable?
The less risk you can tolerate or accept the more process you need, the more knowledge and skills, and the more effective your methods and tools need to be
The more your project needs to be completed by a specific date, at a specific cost, and deliver specific deliverables and behavior the more you need a project management process
Project management balances the 3 sides of a triangle, Schedule, Cost, and Deliverables Quality
These 3 elements are interrelated, change one or when you absolutely need to meet one the other two will be affected
Assumptions Drive Risk:
Identify what’s being assumed
If you assume something will or won't happen that's a risk
Assign someone on the core team record assumptions and identify risks
To identify what someone is assuming observe what’s stated and implied
Validate assumptions
Ask seemingly dumb questions
"It appears that you're assuming that..., is that true?
Describe the risk items
Quantify & prioritize each item
Quantify each risk item’s impact on a scale of 1 – 5 with 1 = low, 5 = high & probability % that it will happen.
Multiply impact X probability. Example Impact 4 X Probability of 95% 4 X .95 = 3.8.
Develop a mitigation plan for the top items & include the mitigation plans in the project.